Rains delay P13-B hydro projects in Bukidnon

Construction of the P13-billion twin hydroelectric projects of Hedcor, Inc. is being delayed due to geological conditions and continuous rains, company officials said on Tuesday.

Gregorio Jabonilla, Hedcor vice-president for business development, told reporters that the two run-of-river hydro projects have already been delayed for 110 days when their workers encountered problems at their work site in this municipality.

“Our workers are encountering soft rock during our excavation work. The sides of the mountain keep on collapsing on us,” he said.

The Hedcor run-of-river hydro projects are expected to generate 68.8 megawatts of electricity. The project cuts across Guehean, Amusig and Tanaon rivers and empties into the Tagoloan river.

Read more here.
Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s